Noida International Airport (Jewar Airport) : An Overview

Flughafen Zürich AG (Zurich Airport) is developing Jewar Airport south of Greater Noida, with a 4-phase master plan designed to handle 60 million passengers per annum in the future. The project is also known as Jewar Airport.

Noida International Airport

  • State â€“ Uttar Pradesh
  • District â€“ Gautam Buddha Nagar district
  • Area â€“ 1,334 hectares
  • Estimated Cost â€“ Rs. 29,650 crore
  • Runways â€“ 2(6 in future)
  • Terminals â€“ 4
  • IATADXNICAOVIND
  • Owner â€“ Noida International Airport Limited (NIAL)
  • Architects â€“ Haptic Architects, Nordic, Grimshaw and STUP
  • Operator â€“ Yamuna International Airport Private Limited (YIAPL) – 100% subsidiary of Zurich Airport International
  • Civil Construction ContractorTata Projects (TPL)
  • Deadline â€“ April 2025

The Airport will have 2 runways in stage-1. it will be developed in four Phases, phase-1 to be completed by April 2025, and final phase-4 to be completed by 2050.

Phase, capacity and project cost of stage-1

PhaseCapacity(Million Passengers per annum)Project Cost(crores)Period
Phase-1124,588FY23-FY27
Phase-2305,983FY31-FY32
Phase-3508,415FY36-FY37
Phase-47010,575FY40-FY50
Source: YEIDA

Phase-1

Noida International Airport phase-1
  • Runway 4150*45 for code E
  • ATC tower
  • Terminal building and cargo terminal
  • Apron
  • Taxiway and other utilities and pffices.

Phase-2

Noida International Airport phase-2
  • 2nd Runway and Taxiway.
  • 2nd Terminal building
  • Cargo extension

Phase-3

Noida International Airport phase-3
  • 2nd Taxiway for Southern Runway
  • 3rd terminal building
  • cargo and Apron Extension

Phase-4

Noida International Airport phase-4
  • 2nd Taxiway for northern Runway
  • 4th terminal building
  • cargo and Apron Extension

Image source: NIAL

Owners

GoUP37.50 %
Noida37.50 %
Greater Noida12.50 %
YEIDA12.50 %
Total100 %
stake holders of NIAL.

Connectivity

Noida International airport will be well connected with Highways, railways and Metro Network.

Road
  • Yamuna Expressway( Greater Noida to Agra).
  • Eastern Peripheral Expressway (Palwal to Ghaziabad).
  • New 31 KM Expressway from Jewar Airport to Delhi Mumbai Expressway(under Construction).
  • Proposed Palwal TO Khurja Expressway.
Railway
  • Planned Ghaziabad-Jewar RRTS rapid rail system.
  • Palwal-Noida International Airport-Khurja Railway.
  • Planned to connect with Noida and Delhi Metro network.

Scroll to Top